CULVERT AND ROADWORK Proj: 9129532-5
Gatineau, Communauté urbaine de l'Outaouais, comté QC CONTEMPLATED
chemin Pink - Phase I, entre la rue de la Gravité et le corridor Deschênes
$9,000,000 est
Note: Project is on hold pending provincial and municipal approvals and funding. Design, tender for the general contractor and construction schedules have yet to be finalized. Further update late 2013.
Project:proposed construction of the first culvert of 0.45 km between intersections with Gravité Street and Grives Boulvard.
Development:Engineering
Category:Bridges; Roads
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Jan 06, 2011. Last report Fri Jun 15, 2012.
This report Tue Dec 18, 2012.