| Note: | Sub trade pricing is being accepted by the construction manager and can be followed under report number 9152695. Phases One, Three, and Four can be followed under report numbers 9127659, 9136151, and 9136157. |
| Project: | concrete foundation, reinforced concrete foundation, cast-in-place concrete structural frame, structural steel frame, masonry exterior, fuel fired heating system, package air conditioning/heat pump system, 02315; excavation, 02935; landscape, 04080; masonry, 08800; glazing systems, 13850; fire alarm, 14240; hydraulic elevators, construction of a condominium apartment building with 500 units. The building will have 100,000 sq ft of retail at the ground level. |
| Scope: | 600,000 square feet; 44 storeys; 5 storeys below grade; 500 units; parking for 1050 cars |
| Development: | New |
| Category: | Apartment bldgs; Retail, wholesale services |
| Owner | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Const manager | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Architect | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Structural cons eng | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Mechanical cons eng | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Electrical cons eng | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|