A 328-tonne bridge is lifted between the two towers of the Concord Adex development known as Parade. Planning for the challenging 12-hour lift took more than three years to organize.
Sky bridge lift successful at Concord Adex condos in Toronto
Plans to hoist a sky bridge spanning two condominium towers in Toronto recently took more than three-and-a-half years of planning.
The 328-tonne bridge now connects two towers, Block 26 and Block 29, part of the Concord Adex development known as Parade. The lift of the structure was engineered by Western Mechanical Electrical Millwright Services Ltd. of Barrie, Ont.
“Construction manager PCL Constructors Canada Ltd. called us in very early in the project as part of an integrated design process,” says Mark Carney, a structural engineer with Western Mechanical. “Anyone potentially involved with the project came to the table early on so they could present the input necessary to complete the project successfully.”
View Larger Map
The sky bridge is three storeys tall and connects the buildings at the 33rd floor and above. Billed as the world’s highest residences on a bridge, the feature will provide residents of the two units with a one-in-a-million view of both the lake and the city to the north. A common area will also run the length of the structure.
The design of the bridge, developed by structural engineers at Halcrow Yolles, a CH2M HILL company, incorporates expansion joints and bearings similar to those used in highway bridge construction, to accommodate any wind movement between the two towers. The bridge was built in sections off site by Walters Group of Hamilton, and then assembled at the project site at ground level.
■ Daily Commercial News subscribers may view more information on Western Mechanical Electrical Millwright Services and its construction projects by viewing company ID 47919 in Reed Construction Data Canada Building Reports.
If you are not already a subscriber, you can be by filling out the form at this web page.
Building Reports are published daily in the Daily Commercial News. The Daily Top 10 Construction projects can be viewed online free of charge at the Reed Construction Data Canada Building Reports web page.
To learn more about construction project leads from Reed Construction Data, fill out the web form at this web page.
“We presented PCL with a plan to use strand jacks to lift the bridge into place,” says Carney.
“To do that successfully, Walters arranged to have steel beams fixed to the concrete pedestals in the mechanical penthouses of both buildings and we pre-determined the load needed to place on the strand jacks.”
Two fixed steel beams were installed in the square building, Block 26, while a single pivoting steel beam was installed in the round building, Block 29. The steel support beams are too heavy to remove from the building, so they’ll remain permanently in the building on the mechanical floor.
Western Mechanical representatives had increased their presence at the site since March. Three strand jacks, each capable of lifting more than 200 tonnes, were delivered to the site two weeks ago and fixed to the extended steel beams.
“At that point, the bridge was pretty much assembled,” says Carney. “Flynn Canada Ltd. was putting the finishing touches on the bridge by installing glass and insulation and electrical work was also being completed. We decided early on that the floor of the bridge would be poured only after the structure was lifted into place, to reduce the load. A vertical concrete pump line was installed along Block 26 to pump concrete into the bridge later on.”
The lift began on the night of Monday, June 26th at 11:30 pm. Because the bridge spans two buildings entirely on private property, no roads were closed. Only a pedestrian walk was declared off limits for the duration of the operation.
“You can never have a perfect situation with wind, so we provided extra stability with the use of four cranes on the ground, supplied by ALL Canada Cranes & Aerials, Limited,” says Carney. “The high capacity cables were anchored through a ballast and snatch block installed on the ground, then fed up to the corners of the bridge and tensioned.”
A Western Mechanical operator initiated the computer-controlled strand jacks to lift the sky bridge slowly into place, carefully monitoring the loads on each jack to ensure a level load. The four ground-level cranes also monitored the tension on each cable.
“To nestle the sky bridge in place against the square building, the pivoting beam rotated the other end of the bridge into place against the round building,” says Carney.
“Walters then shimmed the bridge and welded the shims into place.”
The operation was completed in 12 hours. Carney himself was called back to the office just before the piece de resistance.
“I missed the last part,” he says. “But we planned the job carefully — I knew it was going to be a great success.”
| MOST POPULAR STORIES |
- OPG $1 billion proposal to bury nuclear waste up for comment
- Hundreds of workers to be out of work as Caterpillar Inc. is set to close Toronto factory
- Ontario prompt payment bill to get second reading today
- Construction on pedestrian tunnel to Billy Bishop Airport continues to make progress
- Proposed Ambassador Bridge twinning draws Windsor mayor’s ire
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
SENIORS CONDOMINIUM APARTMENT & OFFICE BLDG
$90,000,000 Richmond Hill ON Prebid
$82,000,000 White River Twp ON Tenders
CONDOMINIUM APARTMENT BUILDING
$40,650,000 Markham ON Prebid
| CURRENT STORIES |
- VIDEO: Competing in the trades
- Multi-employer approach needed in apprenticeships
- New Perspective
- ACEC’s input helps develop global engineering guidelines
- Clerk of works position gives peace of mind on projects
- World Trade Center developer’s plan for a 926-foot tower moving ahead
- Call for action after MOL says workers are responsible for their own safety
- Cold spring and weak construction hurt Deere’s 2013 predictions
- CanBIM reschedule June session
- More green roofs top Toronto buildings
- Witness recants testimony in Montreal corruption case
- Construction Site Arson
- Journal of Commerce Update for the week of May 20th, 2013
- Industry reacts to surprise B.C. Liberal majority
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More