October 28, 2010

Project progress

EllisDon continues construction on Hospital for Sick Children research facility

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

The site of the new Hospital for Sick Children research tower in downtown Toronto was a hive of activity Oct. 21 as concrete was poured for the building’s “mat” foundation.

A total of 1,600 cubic metres of concrete were poured continuously over a 12-hour period. Sitting on top of 20 caissons, the foundation is 35.75 metres long, 14.7 metres wide and 2.5 metres high.

General contractor EllisDon supervised the pour. Ready-mixed concrete supplier St. Marys CBM mobilized three Toronto-area plants. The 750,000-square-foot facility was designed by Diamond + Schmitt Architects with HDR Inc. The team includes structural engineers Halcrow Yolles and mechanical-electrical engineers H.H. Angus & Associates Ltd. The 21-storey research and learning tower will be the largest such high-rise facility in Canada. Completion is scheduled for 2013.

Print | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 481 projects with a total value of $2,274,238,471 that Reed Construction Data Building Reports reported on Wednesday.

CONDOMINIUM, RETAIL AND OFFICE DEVELOPMENT

$150,000,000 Ottawa ON Negotiated

ROADWORK, DRAINAGE, BRIDGE

$135,000,000 Toronto ON Tenders

ROADWORK, DRAINAGE, BRIDGE

$82,000,000 Toronto ON Tenders

Daily Top 10

CURRENT STORIES
TODAY’S TOP JOBS

Project Manager
Ontario-Oshawa

Estimator
Ontario-Toronto

Site/Field Coordinator
Ontario-Mississauga

Superintendent
Alberta-Red Deer

Operations Foreman
British Columbia-Vancouver

Earthworks Estimator
Ontario-King

Junior Construction Manager
Alberta-Fort McMurray

Estimator/Project Manager
Ontario-Gormley

Machinist
Alberta-Edmonton

Heavy Duty Mechanic
Alberta-Edmonton

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design