LATEST NEWS
Sewer & Watermain | Concrete | Roadbuilding | Building Envelope | Steel | Water & Wastewater
April 23, 2009
PIPEFLO CONTRACTING CORP.
Crews from contractor PipeFlo entered a 25-metre-deep shaft to inspect a cracked sewer line while staying in voice contact with a surface unit.
Pipeflo crew takes a close look at deeply buried Hamilton sewer line
The typical Canadian sewer line runs no deeper than about four metres below the surface. A 270-metre length of sewer line running north from the intersection of Locke Street and York Boulevard in Hamilton lies more than 25 metres below the surface — and it needed repair.
“Everything in the system runs on gravity to achieve flow, so the line winds up that deep in order to maintain the grade,” says Kevin Bainbridge, Senior Project Manager of Infrastructure Programming, Public Works, with the City of Hamilton.
“The pipe was installed in 1960 as part of the Western Sanitary Sewer Interceptor using a manually-operated boring machine to dig the tunnel, and poured-in-place concrete — effectively the pipe was constructed inside the tunnel.”
The volume of concrete used in the pipe is high, with a diameter of approximately 1500 mm with 375-mm thick walls. Inspections undertaken in 1999 revealed cracking in the walls of the pipe.
“In the 1960s there wasn’t a lot of understanding of the way concrete set and we believe the cracking was the result of the curing process,” says Bainbridge.
“What came out of the inspection was our belief that there was potential for having fine ground material infiltrate through the cracks and creating cavities around the pipe that would cause structural failure of the pipe over time.”
Video inspections undertaken by PipeFlo Contracting Corp. of Hamilton and CRA Consultants in 2006 revealed that the cracking hadn’t gotten any worse since the original inspection.
PIPEFLO CONTRACTING CORP.
An underground view of the pipe inspection process.
PipeFlo and R.V. Anderson Associates Ltd. were then contracted to develop a plan of attack to see what could be done to rehabilitate the line.
That also allowed PipeFlo to test and verify the entry procedures for operating at the standpoint.
“The timing of the job depends on the sewer usage at any time, so went in at night when there’s a lot less flow and people aren’t using the toilet and the laundry and showering,” says Bainbridge.
A diversion tank constructed about 10 years ago to handle storm water would be used to contain the sewage flow to provide a window of operation for the contractors.
“We were willing to divert the flow to the point that we used 25 per cent of the tank’s capacity,” says Bainbridge.
Three PipeFlo crew members entered the pipe on the night of Feb. 23, with one stationed in the shaft and two going part way into the pipe and sending inspection equipment ahead. A surface unit maintained constant voice contact with the underground crew.
During a dry run, PipeFlo sent two different ground-penetrating radar (GPR) units about 10 metres into the pipe to determine which would be most suitable for the next entry.
“At the time the line was built, they didn’t keep such careful records of the construction methods and materials they used, says Bruce Noble, president of PipeFlo.
“We weren’t sure what the consistency of the concrete would be, or whether there was rebar in the pipe.”
The tank diversion also proved a success.
“At the end of the test run, the tank was only filled to six or seven per cent of its volume,” says Bainbridge. “So we were comfortable that we had a margin of error that would allow a full 12-hour shift.”
The pipe was then examined for debris, which was to be flushed out using a special cleaning nozzle. On next entry, the GPR device was to be used to ensure that no voids existed beyond the pipe walls.
“This is a high-risk environment, and putting people in pipes like this is the last thing we prefer to do,” Bainbridge said.
“In this case, it was determined that sending people down was the only way to examine and deal with the problem.
He said manual repair of the cracks during a 12-hour shift looked like the likely plan.
| MOST POPULAR STORIES |
- New technology allows concrete to come clean
- Ontario architects, general contractor associations issue joint HST bulletin
- WSIB report a clear response to ideas we submitted, Ontario General Contractors Association chief says
- Ground broken on the Cathedral Centre in Toronto
- Highway construction crew uncovers ancient B.C. glacier
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 342 projects with a total value of $2,911,425,288 that Reed Construction Data Building Reports reported on yesterday.
SUBWAY STATIONS, BUS TERMINALS, SUBWAY EXTENSION
$500,000,000 York Reg ON Prebid
$112,000,000 Ottawa ON Prebid
CONDOMINIUM, RETAIL & HOTEL DEVELOPMENT
$100,000,000 Burlington ON Prebid
| CURRENT STORIES |
- Fraud charges laid against former head of Quebec labour union
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Province holding information sessions on new Ontario accessibility standard
- Work continues on Market Wharf condo in Toronto
- Chilliwack Cultural Centre project sets tilt-up concrete record
- WSIB report a clear response to ideas we submitted, Ontario General Contractors Association chief says
- SNC-Lavalin subsidiary Profac under scrutiny over federal contract billing
- As prices surge, China may raise interest rates
- Canadian soldiers repair blown-up bridge in Afghanistan
- Canadian Mechanical Contracting Education Foundation offering Gold Seal course for supervisors
- Slovak construction minister sacked amid corruption scandal
- Historic Kingston Dry Dock restored, enhanced
- Centre for Energy Innovation in Windsor, Ontario built using Termobuild HVAC system
- Canadian Standards Association parking garage standard gets tougher
- Accelerated schedules a challenge for vinyl flooring
- Good materials, shoddy workmanship produces poorly performing floor
- Government takes over Northwest Territories P3 bridge project
- Canadian construction experts visit earthquake-ravaged Haiti
- Winnipeg gets new water treatment plant
- Weighing in on the Tercon Contractors appeal decision
- Construction restarting on hospital in Fort St. John, British Columbia
- In new movie, Hamilton construction worker becomes ‘Defendor’ at night
- ‘Quality product cannot come from cutting corners on safety’
- Shop owner suing VANOC over pre-Olympics road construction disruptions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More







