Work moves upward at the St. Gabriel Village condominium and townhouse project in North York, Ontario.

Shane B. makes progress on St. Gabriel Village project

Owner/developer/general contractor/project and construction manager Shane B. Inc. began the project in August 2006.

Designed by Rafael + Bigauskas Architect Inc., the project includes two 19-storey towers, one 12-storey tower, one eight-storey tower and 23 townhouses. There will be a total of 425 units, three levels of underground parking for the towers and one level underground for the townhouses.

The eight-storey tower featurs ground-floor retail space.

Consultants are Adjeleian Allen Rubeli Ltd. (structural); TeGi Engineering (mechanical/electrical); and Strybos Associates (landscape).

Subcontractors include Lions Group Inc. (excavation); Deep Foundations Contractors Inc. (shoring/caissons); Res Precast Inc; Res Group (formwork); Salit Steel (rebar supply); All Railings (structural steel); St Marys CBM (concrete supply); Res Masonry; Cooltech Air Systems (AC/ventilation) D. Zentil Mechanical (plumbing/sprinklers); Centennial Electric Ltd.; Primeline Windows Inc.; Protech Roofing (roofing/waterproofing/traffic topping); Otis Canada Inc. (elevators); and T. Geopfelt Gardening (landscape).

Print | Email | Comment

ALEX’S BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.

Economics Blog    More 

Lifestyle Blog    More 

PROJECT NEWS BRIEFS

FEATURED CAREER AD

More careers...