DCN ARCHIVES

September 27, 2004

Tower Project

Exterior work progresses for the Mars Parcel ‘C’ research and development tower (background) at College and Elizabeth streets in Toronto.

Construction manager EllisDon Corp. began the 15-storey tower for owner Mars Discovery District in February 2003 and completion is scheduled for this December. The tower will include two levels of underground parking and ground floor retail.

The project was designed by Adamson Associates.

Consultants are: Halsall Engineering Ltd. (structural); Smith & Andersen Consulting Engineers (mechanical/electrical); and JBM Landscape Architects.

Subtrades include: York Excavating & Grading Co. Ltd.; Anchor Shoring & Caissons Ltd.; EllisDon Forming; Harris Rebar (rebar supply); Ontario Redimix Ltd. (concrete supply); Modern Niagara Toronto Inc. (mechanical); Ampere Ltd. (electrical); Vipond Inc. (sprinklers); Sota Glazing Inc. (windows); and Otis Canada Inc. (elevators).

Photo by WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

Print | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 371 projects with a total value of $1,936,826,394 that Reed Construction Data Building Reports reported on Thursday.

GOVERNMENT OFFICE TOWER

$134,000,000 Toronto ON Prebid

CONDOMINIUM APARTMENT BLDGS, TOWNHOUSES, RETAIL

$128,250,000 North York ON Prebid

CONDOMINIUM APARTMENT BLDG, OFFICES, RETAIL

$100,000,000 Toronto ON Prebid

Daily Top 10

CURRENT STORIES
TODAY’S TOP JOBS

Experienced Site Superintendent
Ontario-Cobourg

Project Manager
Ontario-Oshawa

Estimator
Ontario-Toronto

Site/Field Coordinator
Ontario-Mississauga

Superintendent
Alberta-Red Deer

Operations Foreman
British Columbia-Vancouver

Earthworks Estimator
Ontario-King

Junior Construction Manager
Alberta-Fort McMurray

Estimator/Project Manager
Ontario-Gormley

Machinist
Alberta-Edmonton

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design