LATEST NEWS
Roadbuilding | Steel | Heavy Equipment | Concrete | Trade Contracting
April 28, 2008
RICHARD GILBERT
This rebar tower fell over during construciton of the Pitt River bridge just outside Vancouver. Repairs to replace it will be part of the job’s contract price.
Rebar fall won’t delay Pitt River bridge job
Crane body contacted guy wire, ministry investigation reveals
Vancouver
Workers building the new Pitt River Bridge are assessing the damage and developing a plan for repairing the structure after a rebar column toppled.
A nine-metre tower of rebar, which will form one of the support pylons for the bridge, fell over in the early hours of April 14 when a crane came into contact with a guy wire.
The B.C. Ministry of Transportation owns the bridge and the general contractor is Peter Kiewit Sons Co.
At about 6:30 on the day of the incident, one of the supports was damaged and a tower of rebar fell over. Initial reports indicated that one of the guy wires holding the rebar in place was severed by a crane operator and another one was hit.
However, Ministry of Transportation spokesperson Susan Williams says that wasn’t the case.
“The crane did not cut the guy wire. The crane body came in contact with one of the corner guy wires, pulling the cage over,” said Williams. “The crane was not performing a lift at the time of the incident. It was being repositioned.”
No one was hurt in the incident.
“The structural engineers and designers are reviewing the condition of the pylon and rebar, and working with Kiewit to provide a suitable repair procedure which will ensure the structural integrity of the bridge,” Williams said in an e-mail.
“Any concrete damage was minor in nature and can be repaired with standard procedures to allow the next lift to be poured on top as planned.”
Repairs are underway and are expected to continue without affecting construction on the rest of the site.
“The detailed repair procedures are still to be determined, but will likely include straightening and appropriate testing of the lower bars, fabrication of a new rebar cage and minor surface repairs to existing concrete,” Williams said.
Despite this setback the bridge is scheduled for completion in late 2009.
“The remaining five pylons are proceeding on schedule without impact,” she said.
“Any delay to the damaged pylon will be recovered by bringing in additional resources and working extra shifts if necessary, such that the overall bridge schedule will not be impacted.”
The ministry also said it was not possible for the nine-metre tall rebar tower to fall into traffic on the old bridge running through the construction site.
“It (the rebar lift) is mechanically coupled to the previous rebar lift which is in turn embedded in concrete,” explained Williams.
“The couplers are stronger than the bars themselves, so bending over of the cage in place is the worst that could occur.”
The cost of the repairs is not known at this time. The contract is a lump sum, fixed-price contract and as such, any repair costs are included in the contract price.
The contractor is in the process of building part of each of the six supports for the bridge deck. The supports are built by pouring concrete into stacked rebar cages.
The old Pitt River Bridge is a swing bridge that spans the Pitt River between Port Coquitlam and Pitt Meadows, B.C.
| MOST POPULAR STORIES |
- Professional Engineers Ontario unveils new performance standards for demolition
- British Columbia’s construction unions and contractors ratify agreement on drug testing
- Digging deep at Tucker Hi-Rise’s X Condos project
- Deaths of SNC-Lavalin workers in Algeria highlight risks of overseas operations
- Toddglen Construction builds new Neighbourhood on Bloor Street
- 20 Most Popular Stories
| CURRENT STORIES |
- Lineup at the Bars in Toronto
- Industry welcomes $1.1 billion investment in infrastructure by Ontario
- Ontario Association of Architects produces client hiring guide
- Macivor moving on from Ontario industry secretariat
- Behind the Post in Etobicoke, Ontario
- Video Editorial: U.S. trade deficit remains stuck at $700 billion
- Integrated Team Solutions is the preferred proponent for Woodstock, Ontario hospital
- GO Transit wraps up Lakeshore expansion job
- Norwegian solar panel firm to build Quebec plant
- Columns installed in London Olympic stadium
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Industrial Construction is Resource-related (August 28, 2008)
- Construction Starts are Down about One-quarter So Far this Year (August 22, 2008)
- Canada’s Slide in Housing Starts Begins (August 21, 2008)
Lifestyle Blog More 
- What’s Red, Pretty and Prickly? (August 26, 2008)
- What’s Happened to Jokes Isn’t Funny (August 25, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Salter Pilon Architecture Inc. wins contract to design Bradford recreation centre (Aug 22, 2008)
- Shore Tilbe Irwin & Partners begin designs for LEED Silver-compliant community centre (Aug 22, 2008)
- Salter Pilon Architecture nears completion of Georgian Manor working drawings (Aug 22, 2008)
- Town of Markham proposes new LEED-compliant Cathedral Town firehall (Aug 22, 2008)
- Townline Group plans redevelopment of former Fantasy Garden World property (Aug 18, 2008)
