LATEST NEWS
Concrete | Roadbuilding | Heavy Equipment | Sewer & Watermain
April 25, 2008
Seattle project team copes with settling of Viaduct
Seattle
Work to reinforce part of Seattle’s Alaskan Way Viaduct may have contributed to the latest settling of the structure, but officials think that once the project is done, the settling will stop, according to a recent report in the Seattle Post-Intelligencer.
A crew from contractor C.A. Carey Corp. have finished pouring concrete around the base of a support column below the west edge of the viaduct at Yesler Way, the last of four to be shored up in a US$3 million contract.
By May 3, the area will be relandscaped and blocked-off parking spaces restored, completing an initial step toward removing or replacing the viaduct.
The span has settled into the soil 5 1/2 inches in the Pioneer Square area since the 2001 Nisqually Quake; some settling has occurred since the construction work began. The next inspection of the viaduct for settlement and other damage is scheduled for June. Crews reinforced the structure by drilling six-inch pipes into the ground using water to push them in. Three-inch reinforcing piles then were driven into the casing as far as the bedrock layer and connected to the old foundations.
Viaduct project manager Ron Paananen confirmed that the latest round of settling at the location was detected after the work was done on three of the four columns. He said that occurred because the bridge and the new components compressed, pushing down on the new piling. The injection of water, he said, also may have contributed partly.
The work, once done, should stop the settling, though the inspection could show additional settling of up to one-eighth of an inch, Paananen said. Asked if the work ultimately will stop the settling, he said, “it should.”
Following the project, however, the state will continue restricting heavy truck and bus traffic.
DCN News Services
| MOST POPULAR STORIES |
| CURRENT STORIES |
- Aerialists soar at groundbreaking celebration for Four Seasons Hotel and Private Residences
- More Ontario workers register as apprentices, but rate of completion declines
- China’s construction market offers opportunities, challenges for contractors
- FER Building Solutions plans restoration for Prince Rupert’s historic CN building
- Vanbots oversees smooth progress of Bramalea City Centre Mall project
- Use of dispute resolution services rises in competitive construction market
- TransCanada and ConocoPhillips plan to extend Keystone pipeline to U.S. Gulf Coast
- Refurbishment of Dahla dam could make it a target: defence analyst
- Lack of training blamed for death of Canada Line mobile-crane operator
- Quebec teen dies in collapse of garage under construction
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Some Other Keys to Commodity Pricing (2) (July 18, 2008)
- Some Other Keys to Commodity Pricing (1) (July 17, 2008)
- There are Exciting Answers to the World’s Food Shortage (July 16, 2008)
Lifestyle Blog More 
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
- Which Letter of the Alphabet is the Funniest? (July 7, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- George Brown College wins $61.5 million in provincial funds for Toronto Waterfront campus (Jul 14, 2008)
- Plans get underway for Saline Creek Plateau and Parsons Creek communities (Jul 14, 2008)
- Life Construction seeks trade prices for 500 on Sherbourne condominium project (Jul 14, 2008)
- Working designs nearly complete for Joseph and Wolf Lebovic Jewish Community Campus (Jul 11, 2008)
- Alberta commits $200 million to Federal Building renovation and redevelopment (Jul 10, 2008)
