PCL Constructors continue work on Brampton’s Cassie Campbell Community Centre

Work continues on the Cassie Campbell Community Centre in Brampton, Ont. Construction Manager PCL Constructors Canada Inc. began the project in September 2006. Completion is scheduled for fall 2008.

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

Work continues on the Cassie Campbell Community Centre in Brampton, Ont. Construction Manager PCL Constructors Canada Inc. began the project in September 2006 and completion is scheduled for fall 2008.

The work includes a twin-pad arena, aquatic centre, gymnasium, running track, and fitness centre. The centre was designed by Shore Tilbe Irwin & Partners.

Consultants are Halcrow Yolles (structural); Smith & Andersen Consulting Engineers (mechanical); and Mulvey & Banani International Inc. (electrical); and MMM Group (civil).

Subtrades include American Construction and Excavating; Structform International Ltd. (foundation/formwork); Suto Rebar Installations Ltd.; Benson Steel Ltd./Massimo Enterprises (structural steel); G A Masonry; Urban Mechanical Contracting; OZZ Corporation (electrical/security systems); Bothwell-Accurate Co. Ltd. (roofing/waterproofing); Flynn Canada (Toronto) (siding); Schindler Elevator Corp.; and Aldershot Landscaping Contractors Ltd.

Print | Email | Comment

ALEX’S BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.

Economics Blog    More 

Lifestyle Blog    More 

PROJECT NEWS BRIEFS

FEATURED CAREER AD

More careers...