February 29, 2008
SONCIN
Work in the Simcoe tunnel expansion was extensive but done under the radar to most. Above, girder installation takes extensive work power and precision. At middle, the tunnel footing is completed so work on the roadway can begin. Below, gantry erection takes place under the cover of night when road and train traffic is somewhat diminished.
Unique Challenge
Commuter traffic will gain new corridor as work done daily underfoot and undercover
$40 million tunnel expansion kept trains on track
TORONTO
Under ground and under the radar of passersby, a $40 million Simcoe Street tunnel extension has required military precision to build in one of North America’s busiest railway corridors.
“We could not close down any of the tracks overhead,” says Clyde Crocker, Soncin’s Simcoe Street Tunnel project manager. “The railway could have shut us down anytime if we slowed things down or created a problem.”
Soncin was contracted in May 2006 by Fairmont Developments to construct the extension of Simcoe Street, a four-lane underpass which has 13 active rail lines overhead. Construction had to occur without affecting GO Transit, VIA and CNR rail traffic through the Union Station corridor.
Even though the project unfolded in the heart of Toronto’s railway traffic and was surrounded each day by commuter traffic and nearby condominium construction, no one has really noticed the undertaking on Soncin’s plate, says Crocker.
Some construction sites across the Greater Toronto Area can proceed in isolation without much contact with the public. For Soncin, the public played a major role in its project planning.
“It was quite the undertaking,” says Crocker. “It was a complete team effort to make it all happen.”
The Union Station corridor has the highest train volume for a single terminus location in North America. Excavating 20,000 cubic metres of material and integrating the construction project’s schedule, without interrupting commuter and commercial rail traffic, posed unique logistical challenges.
Regular progress meetings with railway and city officials were held every two weeks.
“We needed to keep everyone in the loop and let them know what came next,” adds Crocker.
A key component in building the tunnel was the readily available supply of precast deck segments nearby. The project required 1.6 kilometres of girders so Soncin constructed a precast facility on site. A total of 153 girders were produced in three months. Fifty-one girders were post tensioned and 102 girders were normally reinforced.
The most challenging aspect of the project, besides working in a tight piece of real estate, dominated by rail traffic, was the schedule for construction itself, says Crocker.
Excavation and construction of the bridge’s abutment and piers occurred during regular weekday working hours. The new bridge’s deck provided the biggest and most meticulous planning challenge as it had to be built in sections and completed on pre-determined weekends between 7 p.m. Fridays and 5 a.m. Mondays.
The methodical phasing of this 20 to 30 feet worth of weekend work required everyone on site to be on the same page, says Crocker. With such a small window for construction on pre-determined weekends, precise installation was required. Soncin created an installation manual and supplied one to everyone who worked on the project.
“The manual detailed everything, right down to the smallest detail,” explains Dennes Soncin, Soncin vice-president.
“We wanted everything clear in everyone’s mind, from the foreman right down to the subs. Everyone understood what their function was.”
The project was divided into seven phases, each consisting of the removal of an existing temporary structural steel trestle, which carried four rail tracks, and replacing it with a fully functional precast concrete bridge. Each phase included the installation of an average of 22 girders.
“This project is our biggest one to date,” says Soncin. “It has been great to see the coordinated effort and there definitely is some pride in working on a project like this.”
Completion date for the project is slated for July 2008.
| MOST POPULAR STORIES |
- Professional Engineers Ontario unveils new performance standards for demolition
- British Columbia’s construction unions and contractors ratify agreement on drug testing
- Digging deep at Tucker Hi-Rise’s X Condos project
- Deaths of SNC-Lavalin workers in Algeria highlight risks of overseas operations
- Toddglen Construction builds new Neighbourhood on Bloor Street
- 20 Most Popular Stories
| CURRENT STORIES |
- Lineup at the Bars in Toronto
- Industry welcomes $1.1 billion investment in infrastructure by Ontario
- Ontario Association of Architects produces client hiring guide
- Macivor moving on from Ontario industry secretariat
- Behind the Post in Etobicoke, Ontario
- Video Editorial: U.S. trade deficit remains stuck at $700 billion
- Integrated Team Solutions is the preferred proponent for Woodstock, Ontario hospital
- GO Transit wraps up Lakeshore expansion job
- Norwegian solar panel firm to build Quebec plant
- Columns installed in London Olympic stadium
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Industrial Construction is Resource-related (August 28, 2008)
- Construction Starts are Down about One-quarter So Far this Year (August 22, 2008)
- Canada’s Slide in Housing Starts Begins (August 21, 2008)
Lifestyle Blog More 
- What’s Red, Pretty and Prickly? (August 26, 2008)
- What’s Happened to Jokes Isn’t Funny (August 25, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Salter Pilon Architecture Inc. wins contract to design Bradford recreation centre (Aug 22, 2008)
- Shore Tilbe Irwin & Partners begin designs for LEED Silver-compliant community centre (Aug 22, 2008)
- Salter Pilon Architecture nears completion of Georgian Manor working drawings (Aug 22, 2008)
- Town of Markham proposes new LEED-compliant Cathedral Town firehall (Aug 22, 2008)
- Townline Group plans redevelopment of former Fantasy Garden World property (Aug 18, 2008)
