LATEST NEWS
Concrete | Trade Contracting | Professional Services | Heavy Equipment | Steel
September 6, 2007
CITY OF KINGSTON
Fans of the Kingston Frontenacs will be sitting in the seats of the city's new $46.1 million sports and entertainment centre on Feb. 22. That's the date EllisDon has promised completion for the facility. Recent labour strife has pushed the opening date one month later than expected.
Infrastructure
Labour issues delay construction of Kingston complex
New delivery date set in time for puck to drop
KINGSTON, ONT.
Kingston’s downtown regional sports and entertainment complex will be open for business in February - just over one month behind schedule.
“Design-builder EllisDon has confirmed and committed to having an operational building ready to host events on Feb. 22,” said Lanie Hurdle, the project’s manager for the City of Kingston.
Originally scheduled to open Jan. 18, the $46.1-million facility has been delayed by labour action.
Ontario’s crane operators went on strike for a week earlier this year, then labourers walked off the job for another three weeks.
The Feb. 22 date is significant because there is a regional hockey game scheduled for the facility. The Kingston Frontenacs will be playing the Belleville Bulls.
EllisDon has guaranteed the opening date and any further delays caused by issues under the control of EllisDon would put the contractor in violation of its contract with the city.
The municipality has been waiting for EllisDon to provide the guaranteed completion date since the strikes wrapped up.
The delay will end up costing the municipality as it had to get an extension on its insurance coverage and some salaries will have to be extended, she said. There will also be some additional costs related to the city’s pre-opening contract with Arcturus SMG, the facility’s service provider.
EllisDon is continuing with steel work on the site, pouring concrete and precast and mechanical work is being done.
The building’s limestone exterior is expected to be going up this week and the building should be completely enclosed by mid-October.
Work will continue on the site until after the Feb. 22 opening date. EllisDon and its people will be reviewing equipment efficiencies, doing architectural finishing and demobilizing.
Hurdle estimated workers will remain on the site for about a month after the opening.
The building received site plan approval last week.
Studies of the centre’s mechanical and generator noise show that they are both within approval levels of the Ministry of Ministry. The city is working with EllisDon to provide acoustics that are equal to those of the John Labatt Centre in London, Ont.
The city plans on opening the building for tours Feb. 21, the day before the official opening and the hockey game.
A fundraising campaign for the centre has brought in more than $533,000, more than one quarter of a $2-million goal. Potential naming rights sponsors will be recommended to Kingston City Council this month.
| MOST POPULAR STORIES |
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Prime site moves from contamination to condo in Cambridge, Ontario
- Mine tower largest steel project ever undertaken by Gorf Contracting
- Concrete from Giants Stadium demolition to be buried on site
- McGuinty: We can’t take our foot off ‘public dollar gas pedal’ too quickly
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 350 projects with a total value of $6,260,468,758 that Reed Construction Data Building Reports reported on yesterday.
$98,000,000 Toronto ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$89,000,000 Toronto ON Negotiated
$50,000,000 Toronto ON Negotiated
| CURRENT STORIES |
- Work continues on Pearl Condos in Toronto
- ‘A good first step forward,’ Canadian construction industry says of U.S. stimulus agreement
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Steel provides structure for historic hotel revival in Port Hope, Ontario
- Ontario businesses scramble to ready for arrival of HST
- Construction continues on Atira Women’s Resource Society housing project in Vancouver
- Five still unaccounted for after Connecticut power plant explosion
- U.S. manufacturing employment up, but construction losses continue
- Peterborough Utilities unveils plan for 10-megawatt wind farm
- China orders local governments to pay workers on private sites
- New deal allows Canadian construction firms to bid on U.S. stimulus projects
- Construction continues on Canadian Natural Resource office in St. Albert, Alberta
- Canadian Construction Association summit zeroes in on industry concerns
- Art Gallery of Alberta addition showcases steel
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Five-year forecast looking up for British Columbia construction industry
- Saskatchewan gets new natural gas trades training centre
- B.C. permit numbers rise while Alberta’s fall
- Trades lack LEED understanding
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- Aecon wins $22 million in contracts for steam generators
- SNC-Lavalin partners with Russian bank to form engineering company
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A review of some global economic and policy expectations for 2010 (February 3, 2010)
- Synopsis of RCD’s webinar on the economic and construction outlooks (January 28, 2010)
- Increasing signs of world and U.S. economies getting back on track (January 28, 2010)
- More






