June 22, 2007
Power line, wind farm projects hold during stringent U.S. review
GREAT FALLS, MONT.
The U.S. Department of Energy plans its toughest environmental review of the proposed power transmission line between Great Falls and Lethbridge, Alta., after farmers complained about the proposed type and routing of the power poles.
In March, the U.S. Department of Energy and Montana Department of Environmental Quality issued a draft environmental study of the 230-kilovolt line. But on June 1, after concluding the project might have “a significant effect upon the environment,” the DOE announced it would complete an environmental impact statement because the joint review no longer was sufficient.
Of the agency’s three levels of review, the EIS is the highest.
The 326-kilometre line, with about 210 kilometres in Montana, would connect the Alberta electric grid with NorthWestern Energy’s transmission system in Montana, allowing up to 300 megawatts of power to be shipped in each direction.
Wind farm developers have said the line is critical to construction of their projects. Three companies have already signed up to use capacity on the line to ship power from wind farms they are planning between Great Falls and the Canadian border.
But some farmers who live along the route object to the use of H-frame poles and placing poles diagonally, arguing both make the transmission line more difficult and expensive to move around. They’re calling for the use of single poles, with no diagonal crossings.
“It certainly seems to be an opportunity for us to keep telling the same story,” Dutton-area farmer Jerry McCrae said of the additional environmental review.
The Alberta Energy and Utilities Board hasn’t scheduled public hearings until October. In April, Canada’s National Energy Board, the equivalent of the U.S. Department of Energy, approved a permit for the tie line. At the end of May, the U.S. Federal Energy Regulatory Commission approved the company’s tariff application, which governs prices to use the transmission line.
Canadian Press
| MOST POPULAR STORIES |
- Ministry of Transportation working with biggest road-building budget in its history
- Lethbridge, Alberta builder spends $2 million to turn water tank into restaurant
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Prime site moves from contamination to condo in Cambridge, Ontario
- Mine tower largest steel project ever undertaken by Gorf Contracting
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 337 projects with a total value of $3,003,381,002 that Reed Construction Data Building Reports reported on yesterday.
$82,000,000 Metro Toronto Reg ON Tenders
CONDO BUILDING, HOTEL, THEATRE, RETAIL
$65,000,000 St Catharines ON Prebid
$40,000,000 Ottawa ON Prebid
| CURRENT STORIES |
- Peel Heritage Complex in downtown Brampton to undergo $11-million renovation
- New deal allows Canadian companies to bid on U.S. stimulus contracts
- ‘A good first step forward,’ Canadian construction industry says of agreement
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Ontario Road Builders’ Association honours volunteers who go the extra mile
- Prime site moves from contamination to condo in Cambridge, Ontario
- McGuinty: We can’t take our foot off ‘public dollar gas pedal’ too quickly
- Five still unaccounted for after Connecticut power plant explosion
- Non-residential permits up in December
- BMO executive sees U.S. housing rebound
- Brazilian dam contract to include $830-million environment levy
- Concrete from Giants Stadium demolition to be buried on site
- New deal allows Canadian construction firms to bid on U.S. stimulus projects
- Construction continues on Canadian Natural Resource office in St. Albert, Alberta
- Canadian Construction Association summit zeroes in on industry concerns
- Art Gallery of Alberta addition showcases steel
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Five-year forecast looking up for British Columbia construction industry
- Saskatchewan gets new natural gas trades training centre
- B.C. permit numbers rise while Alberta’s fall
- Trades lack LEED understanding
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- Aecon wins $22 million in contracts for steam generators
- SNC-Lavalin partners with Russian bank to form engineering company
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A review of some global economic and policy expectations for 2010 (February 3, 2010)
- Synopsis of RCD’s webinar on the economic and construction outlooks (January 28, 2010)
- Increasing signs of world and U.S. economies getting back on track (January 28, 2010)
- More